Playground Renovation

Update May 2016:
Great news! We have broken ground on the large playground and ordered the brand new equipment to be delivered before school dismisses in June! We have enough funds to complete Phase 1 this summer for the start of the 2016-2017 school year~
There will continue to be grading and preparation of the large playground in the next month to get ready for new equipment installation. After the new equipment and swings are installed, we will then lay the grass sod for the new soccer field and finish Phase 1.  We will continue to fund raise within the community and local business to begin Phase 2 which includes: Natural Play Space, Amphitheater Outdoor Area, Outdoor Shade Classroom, and Hill Slide.
Highlights
  • New Playground Equipment Ordered
  • 6-Bay Swing Set Ordered
  • Soccer Goals Being Selected
  • Soccer Field Will Be Ready for grass sod after equipment installation
  • Tether Balls Will Be Relocated
  • Summer Project Items: Lay the grass sod for soccer field, relocate tether balls, paint the existing basketball court with four square games
  • Ribbon Cutting Planned for 1st Phase: Start of School Year, August 2016

We are excited to utilize the PTO funds that were raised this year and last year with the help of ALL our parents, teachers, and staff! If anyone is interested in getting more involved, assisting with additional fundraising outside of the Claxton community, please contact Christy Ramm #828-230-4281 or rammfamily@gmail.com

To contribute financially, use the form below and choose “playground renovation” for the category!

Make a Donation

If you would like to make a donation to benefit our school, please use this form. Thank you so much for your support!
  • We will only use your phone number or email if we need to contact you about your donation.
  • Entering your contact information will allow us to send you a receipt for tax purposes.

To see the pdf files better, click the download link for each file. If an individual or business wishes to make a donation to help fund the playground work, they may click here to visit our Donation page (using PayPal).

——  UPDATED MASTER PLAN (2/11/16)  ——
[gview file=”http://claxtonparents.com/files/2016/03/Claxton-Master-Plan-Revised-2-11-16_24x36.pdf”]

——  LATEST COST ESTIMATE  ——
[gview file=”http://claxtonparents.com/files/2016/03/Claxton-Preliminary-Cost-Estimate_02-19-16.pdf”]

 

——  THE SCHEDULE – timeline of when the work will happen:  ——
[gview file=”http://claxtonparents.com/files/2016/01/SDS-Claxton-Elementary-Playground-Schedule_11-2-15.pdf”]

 

——  THE CONTRACT – with Site Design for the work on Phase 1:  ——
[gview file=”http://claxtonparents.com/files/2016/01/SDS-Claxton-Elementary-Playground_Survey-CD-Scope-_Updated-11-2-15.pdf”]

 